Skip to main content Skip to footer

Capital Projects

Our capital budget funds the construction and repair of the County's infrastructure assets such as roads, bridges, buildings, water mains, sewers, and more.


Current project status

View the engineering programs below for a list of current capital engineering projects in the County. 

Cheapside Road Bridge Rehabilitation

Concession 2, Walpole
July 25, 2025 to TBD
Project Number: ENG-51-2024
Project Lead: Mark Long
Ward: 1
Additional Information: Construction delayed from 2024 to 2025. 


Old River Road Pedestrian Bridge Conversion 

Old River Road, North Cayuga
Start Date/End Dates TBD
Project Number: ENG-50-2025
Project Lead: Mark Long
Ward: 2 & 6
Additional Information: Project awarded, construction to begin Spring 2025.  


Townline Road Pedestrian Bridge 

Haldimand-Dunnville Townline Road, Canborough
Start/End Dates TBD
Project Number: ENG-50-2025
Project Lead: Mark Long
Ward: 4 & 6
Additional Information: Project awarded, construction to begin Spring 2025.  


Lakeshore Road Culvert Replacement

New Lakeshore Road, Dunnville
Start/End Dates TBD
Project Number: ENG-51-2025
Project Lead: Mark Long
Ward: 5
Additional Information: Project awarded, construction to begin Spring 2025. 


Gypsum Mine Culvert Liner

Caledonia Soccer Complex Road
Start/End Dates TBD
Project Number: ENG-51-2025
Project Lead: Mark Long
Ward: 3
Additional Information: Project awarded, construction to begin Spring 2025.


Concession 6 Walpole Culvert Replacement 

Concession 6, Walpole 
Start/End Dates TBD
Project Number: ENG-51-2025
Project Lead: Mark Long
Ward: 1
Additional Information: Project awarded, construction to begin Spring 2025. 


Highway 54 Bridge Removal & Grand Vista Trail 2 Extension

Munsee Street North/Highway 54, Cayuga 
Late Spring - Late Fall 2025
Project Number: ENG-54-2025
Project Lead: Mark Long
Ward: 2
Additional Information: Project to be tendered Spring 2025. 
This project will remove the existing rail overpass bridge on Haldimand Road 54/Munsee Street North in Cayuga and replace it with a new road profile. This project will also include building an AODA compliant trailhead and parking area for the Grand Vista Trail.
A by-pass road will be built on the west side of the Haldimand Road 54/Munsee Street North before the bridge removal to allow traffic to continue through the project area during construction. The Grand Vista trailhead will be completed following the reopening of Haldimand Road 54.
A public open house was held on February 18th, 2025 to review the design of this project and answer any questions. If you require further information, please contact engineering@haldimandcounty.on.ca.

Supply and Placement of Hot Mix Asphalt and CIREAM

Sandusk Road - Highway 6 to Haldimand Road 20, 1st Line - Highway 6 to Oneida Road, Rainham Road - Haldimand Dunnville Townline Road to Lighthouse Drive, Robinson Road - Highway 3 to Bird Road
Start/End Dates TBD
Project Number: ENG-30-2024
Project Lead: Mark Long
Ward: 1, 4, 5, & 6
Additional Information: Project awarded, construction to begin Spring 2025.


North Forks Maintenance

Lowbanks
December 2024 - December 2025
Project Number: ENG-10-2024 
Project Lead: John Van Rooy
Ward: 5
Additional Information: Maintenance not yet started. 


South Forks Maintenance

Lowbanks 
December 2025 - December 2025
Project Number: ENG-10-2024 
Project Lead: John Van Rooy 
Ward: 5
Additional Information: Maintenance not yet started


Maple Creek Maintenance

Dunnville 
December 2025 - December 2025
Project Number: ENG-10-2024 
Project Lead: John Van Rooy 
Ward: 6
Additional Information: Maintenance not yet started


Maple Creek Dunn Branch Maintenance

Dunnville
December 2025 - December 2025
Project Number: ENG-10-2024 
Project Lead: John Van Rooy 
Ward: 5
Additional Information: Maintenance not yet started


Pat Warren Maintenance

Dunnville
December 2025 - December 2025
Project Number: ENG-10-2024 
Project Lead: John Van Rooy 
Ward: 6
Additional Information: Maintenance not yet started


 

2025 projects coming soon

Jarvis Road Reconstruction

Peel Street East - Main Street North to East End, Peel Street East - End to Craddock Boulevard, Keen Street - Peel Street to End, and Walpole Drive - Monson Street to Talbot Street East 
July 29, 2024 to Summer 2025
Project Number: ENG-52-2024
Project Lead: Danielle Fletcher
Ward: 1
Additional Information: Construction was started in 2024, and put on hold for the winter. The project is recommencing April 2025 for completion in early Summer 2025. Some information on the work for each road in the project is below.  

  • Keen Street - Peel Street to End
    Watermain replacement was completed in 2024
    Sewer lining to be completed this Spring/Summer 2025
    Final paving to be completed this Spring/Summer 2025
  • Peel Street East - End to Craddock Boulevard 
    Watermain and sewer replacement were completed in 2024
    Final paving to be completed this Spring/Summer 2025
  • Peel Street East - Walpole Drive East to end
    Watermain and sewer replacement were completed in 2024
    Final paving to be completed this Spring/Summer 2025
  • Peel Street East - Main Street North to Walpole Drive
    Watermain replacement to commence April 2025
    Road resurfacing and curb/sidewalk replacement to follow this Spring/Summer 2025
  • Walpole Drive - Talbot Street East to Peel Street East
    Watermain and sewer replacement were completed in 2024
    Sidewalk replacement and new curb installation to follow this Spring/Summer 2025
    Final paving to be completed this Spring/Summer 2025
  • Walpole Drive - Monson Street to Peel Street East
    Watermain and sewer replacement to commence April 2025
    Sidewalk replacement and new curb installation to follow this Spring/Summer 2025
    Final paving to be completed this Spring/Summer 2025

Caledonia Road Reconstruction

Aberdeen Street - Sutherland Street East to Burke Drive, Gypsum Avenue - Argyle Street North to End, Inverness Street - Caithness Street West to Orkney Street West, Sutherland Street West - Inverness Street to Shetland Street
Start/End Dates TBD
Project Number: ENG-55-2025
Project Lead: Danielle Fletcher
Ward: 3
Additional Information: Project to be tendered. 


Hagersville Road Reconstruction

Athens Street - Sherring Street North to Cedar Street, Tuscarora Street - King Street West to Oneida Street, King Street West - Rail Line to Tuscarora Street
Start/End Dates TBD 
Project Number: ENG-52-2025
Project Lead: Danielle Fletcher
Ward: 4
Additional Information: Project to be tendered. 

Rural Road Resurfacing 

Concession 2 Walpole - Cheapside Urban Boundary to Haldimand Road 53, Erie Street South - Bluewater Parkway to Lakeshore Road, South Coast Drive - Rainham Road to Cheapside Road, Lakeshore Road - Haldimand Road 50 to Haldimand Dunnville Townline Road, Lakeshore Road - Brookers Road to Haldimand Road 50, Sweets Corners Road - Lakeshore Road to Rainham Road, Townline Road West - Haldimand Road 20 to End, Concession 1 Road Seneca - Highway 56 to Caistorville Road, Shoreline Trail - All
Start/End Dates TBD
Project Number: ENG-22-2025
Project Lead: John Van Rooy
Ward: 1, 2, 4, & 5
Additional Information: Project awarded, construction to begin Spring 2025

Highland Storm Water Management Pond Maintenance

Highland Boulevard, Caledonia
July 31, 2024 to December 20, 2024
Project Number: ENG-37-2024
Project Lead: John Van Rooy
Ward: 3
Additional Information: Project is 90% complete. 


 

Dunnville Urban Overlay 

Lock Street West - George Street to West Limit, Pine Street - Lock Street to Alder Street, Griffith Street - Alder Street West to South Cayuga Street West 
Start/End Dates TBD
Project Number: ENG-31-2025
Project Lead: Lucas Hunter
Ward: 6
Additional Information: Project to be tendered. 


Springvale Urban Overlay 

Concession 14 - Urban Limits to Haldimand Road 55, Haldimand Road 55 - Urban Limits to Concession 14
Start/End Dates TBD
Project Number: ENG-31-2025
Project Lead: Lucas Hunter
Ward: 1
Additional Information: Project to be tendered. 

We recognize the impacts of construction on day-to-day activities and strive to complete projects in an efficient and timely manner to minimize disruption to residents, businesses and tourists.

View our Road Closure map for a listing of current road closures in the County. 

Contact Us

Engineering & Capital works
53 Thorburn Street South
Cayuga, Ontario
Canada, N0A 1E0

Email Engineering
Phone: 905-318-5932

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.